SPD and Earthing in ELV Packages: A Sourcing Checklist

SPD and Earthing in ELV Packages: A Sourcing Checklist

By Zoey Zhang, Founder & Lead Sourcing Specialist

ELV

Surge protection in an ELV package is not one device, it is three coordinated stages plus one equipotential plane. Type 1 sits at the incoming supply on a 10/350 us waveform and takes the lightning current, Type 2 at floor boards on 8/20 us takes induced and switching surges, Type 3 at the equipment takes the residual. The hard constraints: Up must stay under 80% of the equipment impulse withstand, and every metre of connecting lead adds roughly 1 kV, so the line and PE leads together are held to 0.5 m. Signal ports follow IEC 61643-21 test classes D1/C2/C3, and PoE ports need Uc of at least 60 V DC and a load rating that carries 1.3 to 1.7 A.

How Exactly Does Cantonmade Sourcing Agent Work?

Watch the full video

    On a hotel ELV quotation, surge protection is one line: SPDs, quantity to be confirmed. Earthing is another line: earth resistance 1 ohm or less. Neither line shows a problem. The problem shows up after the first storm: NVRs and switches fail together, door controllers drop off the network, IPTV set-top boxes come back with blank configuration. Or it shows up at handover, when the SPDs sit in the far corner of the distribution board with half a loop of line and PE lead each, and a device rated Up 1.5 kV presents 3 kV to the equipment it was bought to protect.

    This page covers the part of the ELV package that is normally left as a placeholder: how the stages split, how Up matches equipment withstand, why the leads stop at 0.5 m, how to specify signal ports, how to write bonding and earthing into the drawing, and a ten-line RFQ plus a counted example for a 500-room hotel. No equipment prices, only the numbers you can check.

    Two kinds of overvoltage spend money in different places

    Many quotations treat lightning and switching surges as one item, which produces either over-design (a high-energy device at every socket) or a gap (nothing at floor boards).

    Lightning surgeSwitching overvoltage
    SourceDirect strike via down conductors, or induced on long external linesMotor start and stop, capacitor bank switching, VFDs, UPS transfers
    Standard test waveform10/350 us (simulating lightning current)8/20 us (surge current), 1.2/50 us (surge voltage)
    EnergyHigh, kA level with a long tailLow, more than an order below at the same peak
    Main entry pointIncoming supply, roof or pole-mounted lines, inter-block linksBetween boards inside the same installation
    Device that handles itType 1, including 1+2 combinationType 2, Type 3

    Once that split is clear the configuration becomes one sentence: incoming for lightning, floor boards for induced and switching, the equipment end for residual. Doing it the other way round, a Type 2 at the incoming board and nothing at the equipment, is the most common case of a package that has SPDs and no protection.

    Three SPD types: the test waveform and the position, not the shape

    TypeWhere it sitsTest waveform and main parametersTypical UpTechnology
    Type 1 (class I test)Main board, LPZ 0 to 1 boundary10/350 us, parameter Iimp1.5 to 4 kVSpark gap, gas discharge tube
    Type 1+2Main board or the first board near the entryBoth waveforms, Iimp plus In1.5 to 2.5 kVGap plus varistor
    Type 2 (class II)Floor boards, ELV room distribution boards8/20 us, parameters In and Imax1.5 kV or belowMetal oxide varistor
    Type 3 (class III)At the equipment, ahead of a rack PDUCombination wave 1.2/50 plus 8/20, parameter Uoc1.0 kV or belowVaristor, TVS or hybrid

    Three procurement actions follow. Write the stage and the test class with the discharge current into the RFQ instead of the words surge protector. Ask for the type test report that shows the class and waveform, not just a data sheet. A 1+2 combination saves a board position, but only if the manufacturer has tested the pair as a set rather than assembling two devices in one housing.

    Up has to match the withstand voltage, 80% is the line

    Up is the highest voltage across the SPD terminals during a surge, which is what the downstream equipment actually sees. It has to be checked against the rated impulse withstand voltage in IEC 60664-1:

    Overvoltage categoryTypical equipmentWithstand at 230/400 VUp allowed at 80%
    IVIncoming equipment, meter side6 kV4.8 kV or below
    IIIFixed installation equipment, board components4 kV3.2 kV or below
    IIEquipment fed from a socket, most ELV power supplies2.5 kV2.0 kV or below
    ISensitive electronics, telecom and data equipment1.5 kV1.2 kV or below

    The 80% margin is engineering practice rather than a clause, and the reason is simple: Up is measured at the device terminals, while the equipment also sees the lead drop and some tolerance. Where an ELV room holds both category II loads (switch and NVR power supplies) and category I loads (network boards, AV matrices), the strictest category sets the Up. This is the same order of work as the point count we run in the ELV package page: fix the protection level, then the device, then the quantity.

    The 0.5 m rule: the lead is part of Up

    This is the requirement an installation team breaks most often and a quotation never shows.

    Total lead (line to SPD plus SPD to PE bar)Added voltage at 10 kA, 8/20 usVoltage seen at the equipment (Up 1.5 kV)Against category II, 2.5 kVAgainst category I, 1.5 kV
    0 m01.50 kVpassespasses
    0.25 mabout 0.25 kV1.75 kVpassesover
    0.5 mabout 0.5 kV2.00 kVpassesover
    1.0 mabout 1.0 kV2.50 kVexactly at the limitover
    2.0 mabout 2.0 kV3.50 kVoverover

    The figures come from published guidance rather than from any single clause: BS 7671 section 534 gives about 1,000 V for a 1 m straight conductor at 10 kA 8/20 us and asks for the total lead to be preferably within 0.5 m and never above 1 m; manufacturer technical papers tabulate about 2.5 kV per metre at 25 kA; the same section sets the installed assembly limit at 2.5 kV on a 230/400 V system. The point is that a compliant device on a compliant-looking installation can still be out of specification, and 1 m of lead is enough to use up the whole margin.

    Two actions follow. Reserve a position in the board next to the incoming device and the PE bar instead of the far corner. Where the board layout allows it, connect in a V shape with both conductors landing directly on the SPD terminals, which is shorter than routing to a busbar and back. Conductor sizes follow the local standard and the manufacturer: 16 mm2 copper is common for Type 1, 4 to 6 mm2 for Type 2 and Type 3.

    Backup protection and RCDs: two acceptance failures

    Backup protection. An SPD sits in parallel and carries no load current in normal operation, so its protective device cannot be sized on load current. It has to follow the maximum overcurrent device the manufacturer states, usually a specific fuse or breaker rating. Leave that line out and the site will protect the SPD with the 63 A main switch, which is the same as not protecting it.

    RCD coordination. A Type 1 device can produce power-frequency follow current when it operates, so it is not recommended downstream of an RCD; where it must be, an S-type (time delay) RCD is used. The second point is leakage accumulation: the standing leakage of several varistor-based SPDs plus the equipment leakage can push a 30 mA RCD into nuisance tripping in a wet season, which the client reports as the site tripping whenever it rains. Ask for the standing leakage of each device and add it up per RCD circuit before ordering.

    The most common counter-example in an ELV room: cable bundled in loops with no routing, which is exactly the environment where a 0.5 m SPD lead is impossible

    Signal ports are the largest count in the package

    Power-side SPDs run to a few dozen per project; signal-side devices run to hundreds. Pole-mounted cameras, inter-block fibre and copper links, controllers to locks, lift intercom, roof access points: any line that leaves the building or goes up a pole needs a device at both ends, and protecting only the head end leaves the outdoor section exposed.

    Specify by the IEC 61643-21 test class: D1 (10/350 us, at the building entry, takes lightning current), C2 (1.2/50 plus 8/20 us, at the floor or riser boundary), C3 (close to the equipment, takes the residual). PoE power on the same pair is explicitly within scope, so three numbers get checked together:

    CheckFigureWhy it matters
    Uc, maximum continuous voltage60 V DC or above on a PoE portBelow that, normal operating voltage is consuming device life
    Rated load current IL1.7 A or more (802.3bt Type 4 at 71.3 W on the PD side is about 1.68 A at the 42.5 V limit, 1.25 A at 57 V)Undersized devices run hot, drop voltage, or fail to carry the load
    Transmission ratingCat6A or 10G stated, with insertion loss and return loss figuresA device rated only to Cat5e takes a 10G link back to 100 Mbit

    Two more details: a signal SPD still needs an earth, and the head-end unit has to reach the bonding bar or it protects nothing; and for pole-mounted cameras, fit both ends and use IP66 or better on the pole, otherwise the first wet season ends it.

    Bonding and earthing: write “one common electrode” before quoting a resistance

    Earthing an ELV system is not driving one rod. It is tying the head-end room, floor ELV rooms, tray, racks and metal services into one equipotential plane and then giving the lightning current a path out. On paper that becomes four checkable numbers:

    ItemFigureBasis
    Main equipotential bonding conductor6 mm2 copper minimum, at least half the largest protective conductor, capped at 25 mm2 copperIEC 60364-5-54:2011+A1:2021, HD 60364-5-54
    Supplementary bonding conductor2.5 mm2 with mechanical protection, 4 mm2 withoutSame
    SPD connecting conductors16 mm2 copper common for Type 1, 4 to 6 mm2 for Type 2 and 3National conditions differ; take the larger of standard and manufacturer instruction
    Resistance where one electrode is sharedThe lowest value required by any connected equipmentGB 50343-2012 clause 5.2.5, mandatory

    GB 50343-2012, the Chinese standard for lightning protection of building electronic information systems, came into force on 1 December 2012 and grades protection from A to D, with SPD staging, bonding, shielding and routing all in chapter 5. The one-ohm figure that circulates online is a project target, not a universal requirement: the requirement is the minimum value demanded by the connected equipment, so the RFQ should quote the design value and ask for a resistance test record template rather than assuming a number.

    Tray bonding and continuity are covered in cable tray and conduit sourcing under IEC 61537, and shielding practice in structured cabling sourcing; neither is repeated here.

    Goods-in checks and site testing are the only effective acceptance for this line: data sheet against the delivered unit, and lead length against the drawing, both before energising

    A 500-room hotel, counted

    On the usual arrangement of 20 floors above ground, 2 basement levels, 22 floor ELV or distribution boards, one control room and one front-desk ELV room:

    ItemQuantityHow it is counted
    Type 12One at the utility incoming, one at the generator or standby incoming (required where there is roof air termination or an overhead supply)
    Type 22422 floor boards plus control room plus front-desk ELV room
    Type 33426 ELV room racks ahead of the PDU, plus 8 critical units (NVRs, servers, video matrix)
    Signal SPD6418 pole cameras at two ends, plus 14 inter-block links at two ends
    Bonding bars2322 ELV rooms plus the head-end room
    Bonding branch cable, 6 mm2about 184 mAt an average of 8 m per bar

    The counting method matters more than the totals. Power-side devices follow the board schedule; signal-side devices follow the question of which line leaves the building or goes up a pole. Quotations that count signal SPDs from the camera total (128 channels, 128 devices) buy twice what the project needs; quotations that count by rack leave every pole-mounted run unprotected.

    Ten RFQ lines and five goods-in checks

    Copy these ten lines into the RFQ:

    1. Staging schedule: which class, which board, how many per board, with the board list attached
    2. Test class and waveform: Iimp, In, Imax, Uoc values and the waveform (10/350, 8/20, combination)
    3. Up value and the equipment category it is matched to (II or I)
    4. Backup protection: the OCPD type and rating the manufacturer requires, and whether it is built in
    5. Status indication and signalling: mechanical flag, remote dry contact, and whether it goes to BMS or the monitoring system
    6. Signal side: test class (D1, C2, C3), Uc, IL, Cat6A or 10G insertion loss and return loss
    7. Enclosure rating and mounting: DIN rail indoor, IP66 outdoor
    8. Type test report and certification: which legal entity holds it and whether the number can be verified
    9. Bonding accessories: bars, branch conductor sizes, labelling requirements
    10. Acceptance: earth resistance test record, point-by-point energised check with status confirmation, and who signs

    Goods-in checks, five: verify model and test class unit by unit and open 5% for the body marking; match Up and the discharge ratings against the report; check terminal size against the instruction (a 16 mm2 terminal will not accept a 4 mm2 conductor, so the site will force it); pull two signal devices for continuity and insertion loss; confirm the backup device rating. At site, add three: measured lead length, earth resistance test, and a status window check on every device.

    Six pitfalls

    1. Writing surge protector and no test class. A Type 2 arrives where a Type 1 was specified, and the lightning stage is simply absent.
    2. Getting Up right and ignoring the lead. One metre of lead consumes the entire margin, so measure length at acceptance instead of judging by how tidy it looks.
    3. Protecting only the head end on signal lines. The pole run stays exposed and the surge still arrives at the port.
    4. PoE ports on a Cat5e-rated device. The link negotiates down to 100 Mbit and everyone blames the switch.
    5. Quoting 1 ohm as universal. Without the minimum-value basis there is no defensible answer at handover.
    6. Leaving the SPD and UPS boundary unclear. UPS sourcing answers how long the load runs without power; SPD answers what happens when the voltage spikes within a millisecond. Neither replaces the other. Rack-level distribution is in rack and PDU sourcing, which shares the same bonding and earthing.

    Where this page sits against the rest of the site

    A delivered reference: /case-studies/bassam-hotel-cctv, a hotel CCTV package with the head-end configuration documented.

    If you already have an ELV bill of quantities, send the SPD and earthing lines and we will run them against these ten points, marking which lines are under-specified and which will fail acceptance. Written reply within 48 hours. The RFQ template is free to use, and the contact page has email and WhatsApp.

    Frequently asked questions

    Why does one SPD type not do the job?

    Because energy handling and clamping voltage pull in opposite directions. A device that survives a lightning impulse has a residual voltage around 1.5 to 2.5 kV; a device that clamps below 1 kV cannot survive the current. So the work is split by position: Type 1 at the incoming board discharges the bulk of the lightning current, Type 2 at floor boards takes the residual down a stage, Type 3 at the equipment finishes. The stages also have to be energy coordinated, either by keeping at least 10 m of cable between them or by buying a combination the manufacturer has tested as a set.

    How should Up be read?

    Up is the highest voltage across the SPD terminals during a surge, which is what the downstream equipment sees. IEC 60664-1 rates impulse withstand for a 230/400 V system at 6 kV for category IV, 4 kV for III, 2.5 kV for II and 1.5 kV for I, where category I is sensitive electronics and telecom equipment. Practice is to keep Up at or below 80% of that withstand, so 2.0 kV for category II and 1.2 kV for category I. Reading Up without the equipment category tells you nothing useful.

    Why does lead length matter so much?

    Because the lead is an inductor of roughly 1 uH per metre, and the voltage drop across it during a surge adds directly to Up. Published guidance puts a 1 m length of straight conductor at about 1,000 V under a 10 kA 8/20 us impulse, and around 2.5 kV per metre at 25 kA. So a device rated Up 1.5 kV on a 1 m lead presents about 2.5 kV to the equipment, exactly the category II limit. That is why standards hold the total lead from line to SPD and SPD to the PE bar to 0.5 m where possible and never above 1 m.

    Do signal lines need protection too, and what about PoE cameras?

    Yes, on any line that leaves the building, goes up a pole, or runs between blocks, and at both ends. The product standard is IEC 61643-21, current edition alongside IEC 61643-01:2024, with test classes D1 (10/350 us, building entry), C2 (1.2/50 plus 8/20 us, floor to riser) and C3 (close to the equipment). PoE power on the same pair is explicitly in scope, so three numbers matter together: Uc of at least 60 V DC, a load current rating that covers 802.3bt Type 4 at 71.3 W on the PD side (about 1.68 A at the 42.5 V limit), and a Cat6A or 10G rating with insertion loss and return loss stated.

    Is a 1 ohm earth resistance the right requirement?

    Not as a blanket figure. GB 50343-2012 clause 5.2.5 is mandatory: where lightning, AC working, DC working and protective earthing share one electrode, the resistance must be the lowest value required by any connected equipment. One ohm is a common project target, not a universal requirement, so the drawing and the acceptance sheet should say the design value with a documented basis. The bonding side is usually skipped: main equipotential bonding conductors are at least 6 mm2 copper, not less than half the largest protective conductor and capped at 25 mm2, while supplementary bonding runs 2.5 mm2 with mechanical protection and 4 mm2 without.

    Next step

    Need a quote or a technical answer?

    Tell us the product and the quantity. Our team in Guangzhou sends back pricing, MOQ and lead time within one business day.

    Guangzhou-based sourcing team · Replies in English within 1 business day

    Share this guide:
    WhatsApp