On a hotel ELV quotation, surge protection is one line: SPDs, quantity to be confirmed. Earthing is another line: earth resistance 1 ohm or less. Neither line shows a problem. The problem shows up after the first storm: NVRs and switches fail together, door controllers drop off the network, IPTV set-top boxes come back with blank configuration. Or it shows up at handover, when the SPDs sit in the far corner of the distribution board with half a loop of line and PE lead each, and a device rated Up 1.5 kV presents 3 kV to the equipment it was bought to protect.
This page covers the part of the ELV package that is normally left as a placeholder: how the stages split, how Up matches equipment withstand, why the leads stop at 0.5 m, how to specify signal ports, how to write bonding and earthing into the drawing, and a ten-line RFQ plus a counted example for a 500-room hotel. No equipment prices, only the numbers you can check.
Two kinds of overvoltage spend money in different places
Many quotations treat lightning and switching surges as one item, which produces either over-design (a high-energy device at every socket) or a gap (nothing at floor boards).
| Lightning surge | Switching overvoltage | |
|---|---|---|
| Source | Direct strike via down conductors, or induced on long external lines | Motor start and stop, capacitor bank switching, VFDs, UPS transfers |
| Standard test waveform | 10/350 us (simulating lightning current) | 8/20 us (surge current), 1.2/50 us (surge voltage) |
| Energy | High, kA level with a long tail | Low, more than an order below at the same peak |
| Main entry point | Incoming supply, roof or pole-mounted lines, inter-block links | Between boards inside the same installation |
| Device that handles it | Type 1, including 1+2 combination | Type 2, Type 3 |
Once that split is clear the configuration becomes one sentence: incoming for lightning, floor boards for induced and switching, the equipment end for residual. Doing it the other way round, a Type 2 at the incoming board and nothing at the equipment, is the most common case of a package that has SPDs and no protection.
Three SPD types: the test waveform and the position, not the shape
| Type | Where it sits | Test waveform and main parameters | Typical Up | Technology |
|---|---|---|---|---|
| Type 1 (class I test) | Main board, LPZ 0 to 1 boundary | 10/350 us, parameter Iimp | 1.5 to 4 kV | Spark gap, gas discharge tube |
| Type 1+2 | Main board or the first board near the entry | Both waveforms, Iimp plus In | 1.5 to 2.5 kV | Gap plus varistor |
| Type 2 (class II) | Floor boards, ELV room distribution boards | 8/20 us, parameters In and Imax | 1.5 kV or below | Metal oxide varistor |
| Type 3 (class III) | At the equipment, ahead of a rack PDU | Combination wave 1.2/50 plus 8/20, parameter Uoc | 1.0 kV or below | Varistor, TVS or hybrid |
Three procurement actions follow. Write the stage and the test class with the discharge current into the RFQ instead of the words surge protector. Ask for the type test report that shows the class and waveform, not just a data sheet. A 1+2 combination saves a board position, but only if the manufacturer has tested the pair as a set rather than assembling two devices in one housing.
Up has to match the withstand voltage, 80% is the line
Up is the highest voltage across the SPD terminals during a surge, which is what the downstream equipment actually sees. It has to be checked against the rated impulse withstand voltage in IEC 60664-1:
| Overvoltage category | Typical equipment | Withstand at 230/400 V | Up allowed at 80% |
|---|---|---|---|
| IV | Incoming equipment, meter side | 6 kV | 4.8 kV or below |
| III | Fixed installation equipment, board components | 4 kV | 3.2 kV or below |
| II | Equipment fed from a socket, most ELV power supplies | 2.5 kV | 2.0 kV or below |
| I | Sensitive electronics, telecom and data equipment | 1.5 kV | 1.2 kV or below |
The 80% margin is engineering practice rather than a clause, and the reason is simple: Up is measured at the device terminals, while the equipment also sees the lead drop and some tolerance. Where an ELV room holds both category II loads (switch and NVR power supplies) and category I loads (network boards, AV matrices), the strictest category sets the Up. This is the same order of work as the point count we run in the ELV package page: fix the protection level, then the device, then the quantity.
The 0.5 m rule: the lead is part of Up
This is the requirement an installation team breaks most often and a quotation never shows.
| Total lead (line to SPD plus SPD to PE bar) | Added voltage at 10 kA, 8/20 us | Voltage seen at the equipment (Up 1.5 kV) | Against category II, 2.5 kV | Against category I, 1.5 kV |
|---|---|---|---|---|
| 0 m | 0 | 1.50 kV | passes | passes |
| 0.25 m | about 0.25 kV | 1.75 kV | passes | over |
| 0.5 m | about 0.5 kV | 2.00 kV | passes | over |
| 1.0 m | about 1.0 kV | 2.50 kV | exactly at the limit | over |
| 2.0 m | about 2.0 kV | 3.50 kV | over | over |
The figures come from published guidance rather than from any single clause: BS 7671 section 534 gives about 1,000 V for a 1 m straight conductor at 10 kA 8/20 us and asks for the total lead to be preferably within 0.5 m and never above 1 m; manufacturer technical papers tabulate about 2.5 kV per metre at 25 kA; the same section sets the installed assembly limit at 2.5 kV on a 230/400 V system. The point is that a compliant device on a compliant-looking installation can still be out of specification, and 1 m of lead is enough to use up the whole margin.
Two actions follow. Reserve a position in the board next to the incoming device and the PE bar instead of the far corner. Where the board layout allows it, connect in a V shape with both conductors landing directly on the SPD terminals, which is shorter than routing to a busbar and back. Conductor sizes follow the local standard and the manufacturer: 16 mm2 copper is common for Type 1, 4 to 6 mm2 for Type 2 and Type 3.
Backup protection and RCDs: two acceptance failures
Backup protection. An SPD sits in parallel and carries no load current in normal operation, so its protective device cannot be sized on load current. It has to follow the maximum overcurrent device the manufacturer states, usually a specific fuse or breaker rating. Leave that line out and the site will protect the SPD with the 63 A main switch, which is the same as not protecting it.
RCD coordination. A Type 1 device can produce power-frequency follow current when it operates, so it is not recommended downstream of an RCD; where it must be, an S-type (time delay) RCD is used. The second point is leakage accumulation: the standing leakage of several varistor-based SPDs plus the equipment leakage can push a 30 mA RCD into nuisance tripping in a wet season, which the client reports as the site tripping whenever it rains. Ask for the standing leakage of each device and add it up per RCD circuit before ordering.

Signal ports are the largest count in the package
Power-side SPDs run to a few dozen per project; signal-side devices run to hundreds. Pole-mounted cameras, inter-block fibre and copper links, controllers to locks, lift intercom, roof access points: any line that leaves the building or goes up a pole needs a device at both ends, and protecting only the head end leaves the outdoor section exposed.
Specify by the IEC 61643-21 test class: D1 (10/350 us, at the building entry, takes lightning current), C2 (1.2/50 plus 8/20 us, at the floor or riser boundary), C3 (close to the equipment, takes the residual). PoE power on the same pair is explicitly within scope, so three numbers get checked together:
| Check | Figure | Why it matters |
|---|---|---|
| Uc, maximum continuous voltage | 60 V DC or above on a PoE port | Below that, normal operating voltage is consuming device life |
| Rated load current IL | 1.7 A or more (802.3bt Type 4 at 71.3 W on the PD side is about 1.68 A at the 42.5 V limit, 1.25 A at 57 V) | Undersized devices run hot, drop voltage, or fail to carry the load |
| Transmission rating | Cat6A or 10G stated, with insertion loss and return loss figures | A device rated only to Cat5e takes a 10G link back to 100 Mbit |
Two more details: a signal SPD still needs an earth, and the head-end unit has to reach the bonding bar or it protects nothing; and for pole-mounted cameras, fit both ends and use IP66 or better on the pole, otherwise the first wet season ends it.
Bonding and earthing: write “one common electrode” before quoting a resistance
Earthing an ELV system is not driving one rod. It is tying the head-end room, floor ELV rooms, tray, racks and metal services into one equipotential plane and then giving the lightning current a path out. On paper that becomes four checkable numbers:
| Item | Figure | Basis |
|---|---|---|
| Main equipotential bonding conductor | 6 mm2 copper minimum, at least half the largest protective conductor, capped at 25 mm2 copper | IEC 60364-5-54:2011+A1:2021, HD 60364-5-54 |
| Supplementary bonding conductor | 2.5 mm2 with mechanical protection, 4 mm2 without | Same |
| SPD connecting conductors | 16 mm2 copper common for Type 1, 4 to 6 mm2 for Type 2 and 3 | National conditions differ; take the larger of standard and manufacturer instruction |
| Resistance where one electrode is shared | The lowest value required by any connected equipment | GB 50343-2012 clause 5.2.5, mandatory |
GB 50343-2012, the Chinese standard for lightning protection of building electronic information systems, came into force on 1 December 2012 and grades protection from A to D, with SPD staging, bonding, shielding and routing all in chapter 5. The one-ohm figure that circulates online is a project target, not a universal requirement: the requirement is the minimum value demanded by the connected equipment, so the RFQ should quote the design value and ask for a resistance test record template rather than assuming a number.
Tray bonding and continuity are covered in cable tray and conduit sourcing under IEC 61537, and shielding practice in structured cabling sourcing; neither is repeated here.

A 500-room hotel, counted
On the usual arrangement of 20 floors above ground, 2 basement levels, 22 floor ELV or distribution boards, one control room and one front-desk ELV room:
| Item | Quantity | How it is counted |
|---|---|---|
| Type 1 | 2 | One at the utility incoming, one at the generator or standby incoming (required where there is roof air termination or an overhead supply) |
| Type 2 | 24 | 22 floor boards plus control room plus front-desk ELV room |
| Type 3 | 34 | 26 ELV room racks ahead of the PDU, plus 8 critical units (NVRs, servers, video matrix) |
| Signal SPD | 64 | 18 pole cameras at two ends, plus 14 inter-block links at two ends |
| Bonding bars | 23 | 22 ELV rooms plus the head-end room |
| Bonding branch cable, 6 mm2 | about 184 m | At an average of 8 m per bar |
The counting method matters more than the totals. Power-side devices follow the board schedule; signal-side devices follow the question of which line leaves the building or goes up a pole. Quotations that count signal SPDs from the camera total (128 channels, 128 devices) buy twice what the project needs; quotations that count by rack leave every pole-mounted run unprotected.
Ten RFQ lines and five goods-in checks
Copy these ten lines into the RFQ:
- Staging schedule: which class, which board, how many per board, with the board list attached
- Test class and waveform: Iimp, In, Imax, Uoc values and the waveform (10/350, 8/20, combination)
- Up value and the equipment category it is matched to (II or I)
- Backup protection: the OCPD type and rating the manufacturer requires, and whether it is built in
- Status indication and signalling: mechanical flag, remote dry contact, and whether it goes to BMS or the monitoring system
- Signal side: test class (D1, C2, C3), Uc, IL, Cat6A or 10G insertion loss and return loss
- Enclosure rating and mounting: DIN rail indoor, IP66 outdoor
- Type test report and certification: which legal entity holds it and whether the number can be verified
- Bonding accessories: bars, branch conductor sizes, labelling requirements
- Acceptance: earth resistance test record, point-by-point energised check with status confirmation, and who signs
Goods-in checks, five: verify model and test class unit by unit and open 5% for the body marking; match Up and the discharge ratings against the report; check terminal size against the instruction (a 16 mm2 terminal will not accept a 4 mm2 conductor, so the site will force it); pull two signal devices for continuity and insertion loss; confirm the backup device rating. At site, add three: measured lead length, earth resistance test, and a status window check on every device.
Six pitfalls
- Writing surge protector and no test class. A Type 2 arrives where a Type 1 was specified, and the lightning stage is simply absent.
- Getting Up right and ignoring the lead. One metre of lead consumes the entire margin, so measure length at acceptance instead of judging by how tidy it looks.
- Protecting only the head end on signal lines. The pole run stays exposed and the surge still arrives at the port.
- PoE ports on a Cat5e-rated device. The link negotiates down to 100 Mbit and everyone blames the switch.
- Quoting 1 ohm as universal. Without the minimum-value basis there is no defensible answer at handover.
- Leaving the SPD and UPS boundary unclear. UPS sourcing answers how long the load runs without power; SPD answers what happens when the voltage spikes within a millisecond. Neither replaces the other. Rack-level distribution is in rack and PDU sourcing, which shares the same bonding and earthing.
Where this page sits against the rest of the site
- Power continuity and batteries: /blog/ups-power-supply-sourcing-china
- Cable, shielding and CPR class: /blog/structured-cabling-sourcing-china
- Tray bonding and continuity: /blog/cable-tray-containment-sourcing-china
- Racks, PDUs and U positions: /blog/server-rack-pdu-sourcing-china
- Where LV ends and ELV begins on a quotation: /blog/elv-system-vs-low-voltage
- FAT, integration and handover: /blog/elv-package-delivery-handover
A delivered reference: /case-studies/bassam-hotel-cctv, a hotel CCTV package with the head-end configuration documented.
If you already have an ELV bill of quantities, send the SPD and earthing lines and we will run them against these ten points, marking which lines are under-specified and which will fail acceptance. Written reply within 48 hours. The RFQ template is free to use, and the contact page has email and WhatsApp.