Cable Tray and Conduit Sourcing: Fill, Load, Earthing

Cable Tray and Conduit Sourcing: Fill, Load, Earthing

By Zoey Zhang, Founder & Lead Sourcing Specialist

Sourcing Guide

Tray and containment are approved before the cable, not after: convert the cable count into a cross-section from the maker's outside diameter, keep the fill inside 50% for control and signal cable, state SWL together with the span it was tested at (1/100 lateral deflection, 1.7x SWL before collapse), write EN 50174-2 spacing and the tray form into the drawing and the acceptance sheet, ask for a DIN 4102-12 system report rather than a component report, and price the bonding jumpers into the quotation. A 300x100 tray takes 600 Cat6 cables at 56.5% fill, which is already over the limit.

Last updated: 2026-11-04

Technical China Sourcing Vlog: 2-Day BOQ & QC for CCTV, Barrier Gates, Smart Locks & IP Phones

    The part of a low-voltage package that goes wrong is usually not the camera. It is the cable that will not go in.

    On the drawing, the riser is a single diagonal line; on site, 600 Cat6 cables have to go into a 300 mm wide tray. The quotation says “tray, 300 m” and tells you nothing about width, height or sheet thickness. On acceptance day it turns out there is no bonding jumper and the fire classification came from a component test. All three have the same shape: they are decided before the cable is pulled, and once the ceilings and shafts are closed they cost the ceiling and the shaft to fix.

    This article is not a product catalogue. It gives four numbers a buyer can check - fill rate, load, separation, coating - plus the two acceptance actions: fire and earthing.

    Ladder-type metal cable tray running diagonally below a ceiling, densely filled with network cable

    Photo: Santeri Viinamäki, CC BY-SA 4.0, via Wikimedia Commons.

    1. Tray, trunking and conduit are three products under three standards

    Mixing the names is the most common mistake, and the result is a quotation in which three products share one set of technical clauses.

    CategoryTypical formGoverning standardMain dutyUnit of pricing
    Cable tray (tray / ladder)Ladder, solid-bottom, perforated, wire meshIEC 61537 (third edition 2023 replaced the 2006 second edition; adds SWL test types and an annex on tray used as a protective conductor)Horizontal backbone, comms room, risersPer metre (width x height x sheet thickness) + fittings per piece
    TrunkingClosed wall or ceiling run with a lidEN 50085-1 / -2-1 (slotted trunking inside enclosures falls under -2-3); IEC equivalent IEC 61084 series (EN IEC 61084-2-1:2024)Final runs to workstations, corridor wall runsPer metre + fittings
    ConduitRigid or flexible, metal or plasticIEC 61386 seriesSingle-point final drops, surface and concealedPer metre + saddles

    One-line memory: tray carries the big bundle, trunking carries the banked branches, conduit carries the last cable. A quotation has to separate these three, otherwise you cannot tell whether “300 m of tray” and “200 m of trunking” on the same BOQ are the same goods priced twice.

    2. Choose the form first: five tray types for five situations

    TypeConstructionStrengthDo not use it for
    LadderTwo side rails plus rungsBest heat removal, long spans, easy single-layer dressingAreas where small parts can fall through
    Solid bottomClosed base plateKeeps dust out, holds small items, better screeningDense high-current runs that need to shed heat
    PerforatedPunched baseBalance of heat removal and fixing, the general-purpose choiceDusty workshops - the holes fill up
    Wire meshWelded steel wireLight, flexible on site, well ventilatedHeavy backbones, or anywhere screening matters
    Wide-span / heavy dutyReinforced rails plus intermediate supportsLong spans with fewer bracketsRetrofits with limited headroom

    The perforated metal tray dominates low-voltage backbones because it satisfies three things at once - heat, fixing, and one key condition: under EN 50174-2 the “perforated metal” row gives a far smaller separation than open wiring with no divider (see section 6).

    Perforated galvanised cable tray seen from below, fixed to a ceiling with hanger rods and expansion anchors, green edging

    Photo: Leotard, CC0, via Wikimedia Commons.

    If you want the shape of the whole package first - where the backbone tray, the comms room cabinets and the point drops sit, and who owns each - our hotel low-voltage systems integration page breaks the structure down the same way.

    3. Fill rate: convert outside diameter to cross-section, then pick width and height

    The most common purchasing error is negotiating tray by cable count instead of by cross-section. The calculation is three steps: look up the cable outside diameter, work out the single-cable cross-section, divide by the tray’s internal cross-section.

    Take 600 Cat6 cables at 6.0 mm outside diameter (28.3 mm2 each, 16,965 mm2 in total):

    Tray internal sizeInternal areaFill with 600 cablesEstimated layers (300/400 wide)Verdict
    300x6018,000 mm294.2%12 layers / needs 72 mm heightNot usable, and too shallow
    300x10030,000 mm256.5%12 layers / needs 72 mm heightOver the 50% ceiling for control/signal cable
    400x6024,000 mm270.7%10 layers / needs 60 mm heightHigh, no room to grow
    400x10040,000 mm242.4%10 layers / needs 60 mm heightUsable
    500x10050,000 mm233.9%8 layers / needs 48 mm heightHeadroom for later expansion

    Two rules have to be used together:

    • Fill ceiling: NEC 392.22 gives 50% for a tray carrying control and signal cable only (40% for solid-bottom trays). Power cable has its own table of permitted fill area by tray width (for example 7 in2 at 6 in wide, 14 in2 at 12 in wide) - do not copy the 40% conduit rule across to tray.
    • Expansion headroom: work back from 70% for the minimum cross-section. At 6.0 mm outside diameter that is at least 24,235 mm2; at 6.5 mm outside diameter (a thicker LSZH sheath) it becomes 28,443 mm2 - the same “600 cables”, a 0.5 mm difference in diameter, and nearly a fifth more cross-section needed. That is why the supplier has to calculate from your cable datasheet, not from experience.

    4. Load and span: SWL is a number “at your span”

    A tray is a structural component, not sheet metal. The core of IEC 61537 is the SWL (safe working load) test: at the rated SWL the lateral deflection must stay within 1/100 of the span and the transverse deflection within 1/20 of the nominal width, and at 1.7x SWL the assembly must not collapse. In other words, a supplier who quotes “XX kg/m” without a span has quoted nothing.

    The weight arithmetic (Cat6 at 45 kg/km, confirmed against the datasheet):

    ItemValue
    Weight of one Cat6 cable45 g/m
    600 cables27.0 kg/m
    Plus tray self-weight 3.5-5 kg/m30.5-32.0 kg/m
    Load per bracket at 1.5 m span46-48 kg
    Load per bracket at 3.0 m span92-96 kg

    So the RFQ asks three things: what SWL applies at the span on your drawing (1.5 m / 2 m / 3 m), what hanger rod specification is used, and how additional support at bends and tees is counted. Going from a 1.5 m to a 3 m span halves the bracket count and cuts cost, but the tray specification has to be upgraded with it - this is the item a “cheaper option” quietly changes.

    5. Material and corrosion protection: coating thickness can be measured

    Nine out of ten low-voltage trays are steel; the difference is the corrosion system. Hot-dip galvanising is banded by steel thickness under EN ISO 1461:

    Steel thicknessLocal minimum coatingAverage minimum coating
    Over 6 mm70 um85 um
    Over 3 mm to 6 mm55 um70 um
    1.5 mm to 3 mm45 um55 um
    Under 1.5 mm35 um45 um

    Three comparisons tell you whether a quotation matches:

    1. Hot-dip versus pre-galvanised (such as Z275, 275 g/m2 both sides): pre-galvanised is cheaper and leaves cut edges unprotected; it is adequate in dry indoor space. Outdoors, in basements and at the coast you need hot-dip, or 304/316L.
    2. Powder coating: it looks good but only changes the appearance; cut edges and scratches still rust. State whether the substrate is galvanised before coating.
    3. Non-metallic: FRP is used for severe corrosion, substations and chemical plants. It is non-magnetic and non-conductive, and at the same time it loses the property that makes a metal tray an equipotential body - the earthing design has to be done separately.

    At goods-in, check three things: coating thickness gauge readings against the table above, sheet thickness with a caliper rather than the nominal figure, and whether perforation and welds are continuous. The way tray gets “lightened” is very plain - 1.5 mm sheet becomes 1.2 mm and looks identical.

    6. Power and data in one tray: calculate to EN 50174-2, do not just add a divider

    This is the section most easily fudged verbally. The EN 50174-2 method is minimum separation A = S x P: S comes from the screening class of the information cable and the form of the tray, P from how many power circuits run alongside.

    S (mm, the two common bands):

    Information cable screening classNo divider / open wiringOpen metal trayPerforated metal trunkingSolid metal trunking
    b (ordinary U/UTP Cat6)10075500
    c (screened Cat6/Cat6A)5038250
    d (Cat7/7A class screening)10850
    a (unscreened, low performance)3002251500

    P (counted in 20 A / 230 V single-phase circuits, a three-phase circuit counts as 3):

    Power circuits1-34-67-910-1213-1516-3031-4546-6061-75over 75
    P0.20.40.60.81.023456

    Worked example: U/UTP Cat6 in perforated metal trunking beside eight power circuits gives 50 x 0.6 = 30 mm; the same cable in open wiring with no divider gives 100 x 0.6 = 60 mm. The 0 mm for solid metal trunking has a precondition: the screening performance must equal 1.5 mm steel wall thickness, which stainless steel and aluminium do not meet; perforated trunking also requires the top of the cable to sit at least 10 mm below the top of the divider.

    The purchasing action is one sentence: write the separation and the tray form into the drawing and the acceptance sheet, and require the supplier to state whether a metal divider is included and how thick it is. Without that sentence, site practice is one cable tie around both bundles, and the test fails later.

    7. Fire: accept a system report, not the words “fire-rated tray”

    The dividing line in fire performance is whether a component burns versus whether the circuit keeps working. In low-voltage work the thing that actually has to survive is the second one - the control circuits for fire alarm, escape lighting, fire-fighting lifts and mechanical smoke extraction.

    DIN 4102-12 tests the whole system: tray, supports, hangers, fixings and cable go into the furnace together (furnace temperatures above 1,000 C), and circuit integrity is classified E30 / E60 / E90. The report fixes the permitted support spacing and cable load (commonly the 1.2 m, 10 kg/m band). The usual engineering mapping is: alarm, escape lighting and fire-fighting lifts at 30 minutes (E30); automatic extinguishing and mechanical smoke extraction at 90 minutes (E90) - subject to the local code and the design statement.

    So the RFQ asks for three documents: the system test report (including permitted spacing and load), the cable type used in the test, and the installation instructions. Acceptance measures the support spacing as built - widen 1.2 m to 1.5 m and that report no longer covers your installation. Separately, sealing where the tray passes through walls and floors is done to EN 1366-3, which is a different matter from the tray’s fire classification; one does not substitute for the other.

    Metal cable tray with cables on separate tiers, orange power cable and network cable dressed apart and clamped

    Photo: Leotard, CC0, via Wikimedia Commons.

    8. Earthing and equipotential bonding: put the jumper count in the quotation

    A metal tray is an exposed conductive part and has to be included in equipotential bonding. The verifiable criterion is the IEC 61537 electrical continuity test: at 25 A, joint transition resistance no more than 50 mOhm, and no more than 5 mOhm/m over a 500 mm length with no joint. On site that becomes three actions:

    1. Connect each section with a dedicated bonding jumper or braid - do not rely on the bolted splice alone.
    2. Connect the end of the run reliably to PE, and repeat the bonding per floor in risers.
    3. Put the jumper count into the quotation - “two per section” or “one per 6 m” changes both the price and the acceptance result.

    If the design wants to use the tray body as a protective conductor, IEC 61537:2023 added an annex for exactly that, but the cross-section and connection conditions have to be checked against the annex - do not assume that “metal means it can be the PE”.

    9. Ten lines in the RFQ, and quotations become comparable

    #Required lineWhy
    1Category (tray / trunking / conduit) plus form (ladder / solid / perforated / mesh)Decides which standard applies
    2Width x height (internal clear size)Fill is calculated on the internal cross-section
    3Sheet thicknessThe item most often lightened
    4Material and corrosion system (hot-dip / pre-galvanised / 304 / 316L / FRP plus coating band)Decides service life
    5Span and SWL (state 1.5 m / 2 m / 3 m)SWL without a span means nothing
    6Fitting schedule (bends, tees, reducers, brackets, hangers, bonding jumpers, dividers)Fittings are often 30-40% of the total
    7Whether a metal divider is needed, and its thicknessDecides the power/data separation
    8Fire classification (does it need a DIN 4102-12 system report, E30/E90)Decides whether certified documents are required
    9Surface treatment and cut-edge protection (how site cuts are treated)Decides where the rust starts
    10Packing and marking (length and location reference on every section)Decides how long site spends finding material

    10. Six traps

    1. Negotiating tray by cable count: no outside diameter, no cross-section, and the cables are forced in on site.
    2. Pricing by the tonne: width, sheet thickness and coating are all averaged away, and acceptance has nothing to check against.
    3. SWL without a span: the number in the report belongs to somebody else’s bracket spacing.
    4. Adding a divider instead of calculating separation: divider thickness and material change the S value by a whole band.
    5. Accepting a component report for fire: a tray that will not burn is not a circuit that keeps working.
    6. Leaving bonding jumpers off the schedule: the cheapest quotation is often the one that dropped this line.

    If the project in front of you is a hotel, a campus or a factory low-voltage package, the tray section usually ships with the structured cabling and the rack integration and FAT handover as the same consignment and the same customs entry - read the three BOQs together and the duplicate pricing you remove is usually worth more than the unit price you negotiate.

    If you want a drawing checked for tray cross-section, span and separation, or an RFQ list you can send straight to a factory, send the drawing and the point schedule over: we return an item-by-item review within 48 hours, marking which items must change and which can be optimised. The entry point is contact us, or fill in the parameters with the RFQ template.

    Frequently asked questions

    Should the tray be quoted by weight or by metre - which is easier to approve?

    It depends on what you have to check. A price per tonne can only be checked against material and total weight; width, height, sheet thickness, perforation and coating thickness are all averaged away. A price per metre - with width x height, sheet thickness and coating class stated - can be matched line by line against the drawing. The usual engineering split is: straight sections by metre, fittings such as bends and tees by piece, and supports and bonding jumpers as their own line. Ask the supplier for a total weight at the end, but use it to check the order, not to price it.

    The drawing says 300x100 - will 600 Cat6 cables fit?

    At a 6.0 mm outside diameter, 600 cables come to roughly 16,965 mm2. The internal cross-section of a 300x100 tray is 30,000 mm2, so the fill is 56.5% - already past the 50% ceiling for control and signal cable only, with no room to add cable later. A 400x100 tray (40,000 mm2) brings it to 42.4%, which stays inside the usable band. The safer route is to have the supplier produce a fill calculation from your actual outside diameter and cable count, not a verbal "it usually fits".

    Can power and data share one tray?

    They can, but the separation has to be calculated to EN 50174-2, not settled by adding a divider. For screening class b (ordinary U/UTP) in a perforated metal trunking next to eight 20 A circuits, the minimum separation is 50 mm x 0.6 = 30 mm. Under the same conditions a solid metal trunking can theoretically be 0 mm, but only if its screening performance equals 1.5 mm steel wall thickness - stainless steel and aluminium do not meet that. Put the separation into the drawing and the acceptance sheet, otherwise site practice is a cable tie around both bundles.

    How do I verify a "fire-rated tray" - is the supplier's test report enough?

    Separate a component report from a system report. Under DIN 4102-12, E30/E60/E90 is a result for the whole assembly - tray, supports, hangers, fixings and cable - staying energised inside the furnace, and the report fixes the permitted support spacing and cable load (commonly the 1.2 m, 10 kg/m band). Widen the spacing to 1.5 m on site, or substitute a different cable, and that classification no longer applies. Acceptance needs the system report plus the installation instructions, and a measured check of the support spacing as built.

    Does the tray need bonding jumpers, and does every section need one?

    A metal tray is an exposed conductive part and belongs in the equipotential bonding system, so electrical continuity at the joints has to be assured. The IEC 61537 continuity test asks for a joint transition resistance of no more than 50 mOhm at 25 A, and no more than 5 mOhm per metre on a 500 mm length with no joint. In practice that means a dedicated bonding jumper or braid between sections, a reliable PE connection at the end of the run, and repeat bonding per floor in risers. Put the jumper count in the quotation - it is the line most often dropped, and without it the equipotential test at acceptance fails.

    Next step

    Need a quote or a technical answer?

    Tell us the product and the quantity. Our team in Guangzhou sends back pricing, MOQ and lead time within one business day.

    Guangzhou-based sourcing team · Replies in English within 1 business day

    Share this guide:
    WhatsApp